Hangar Renovation Update

The work has officially begun!  The trucks onsite are for the foundation work.  The sequence will be south to north and west to east.  That way Papa and Oscar will be complete and operational with taxiway F open, all with the goal being to occupy the buildings as they are completed.  The hangar supplier would not begin fabrication until we received the building permits, which I am happy to say occurred  (4/30), from that point it will take them approximately 90-120 days to fabricate and arrive onsite; therefore, we are targeting late August to occupy Papa and Oscar, and late September to occupy Tango, Sierra, and Romeo.

 